A Detailed, Step-by-Step Guide With Checklists, Tables, Tolerances, and Real-World Fixes
Tile can look perfect on day one and still fail months later if the installation is rushed, the surface is off, or the system isn’t built properly. Most tile issues are not “tile problems.” They are prep, planning, bonding, movement, waterproofing, or grout problems — and nearly every failure is preventable.
This guide breaks tile installation down into clear phases and lists the most common mistakes that cause:
-
cracked tile
-
hollow spots
-
lippage (uneven edges)
-
grout cracking or discoloration
-
water leaks
-
loose tile
-
recurring callbacks
Whether you’re a DIY homeowner or a contractor, use this as a pre-install checklist and a troubleshooting reference.
Table of Contents
-
The “Big Five” causes of tile failure
-
Tile installation timeline checklist (fast overview)
-
Phase 1: Subfloor & substrate prep mistakes (most important)
-
Phase 2: Layout & planning mistakes (avoid ugly cuts + crooked lines)
-
Phase 3: Adhesive + troweling mistakes (bond strength & coverage)
-
Phase 4: Large format tile mistakes (flatness, back-buttering, leveling)
-
Phase 5: Wet areas & showers (waterproofing system mistakes)
-
Phase 6: Grout mistakes (colour, cracking, haze, joints)
-
Phase 7: Movement joints, transitions, and perimeter gaps
-
Phase 8: Curing, protection, and first clean
-
Troubleshooting table: symptoms → causes → fixes
-
Room-by-room “do this / don’t do this” tables
-
Contractor handoff checklist (what to document)
-
DIY checklist + when to call a pro
1) The “Big Five” Causes of Tile Failure (Learn These Once)
If you remember nothing else, remember these five.
| Failure Cause | What It Looks Like | Why It Happens | Where It Happens Most |
|---|---|---|---|
| Poor surface flatness / prep | Lippage, cracked tile, uneven grout | Substrate not flat, not clean, not stable | Large format floors, older homes |
| Wrong bonding method / poor coverage | Hollow tile, loose tile, cracked corners | Wrong trowel, thinset skinned, no back-butter | Large tile, floors, wet areas |
| Movement not accommodated | Cracked grout, tenting tile, edge popping | No perimeter gap, no movement joints | Big rooms, sunlit areas, heated floors |
| Water management failure | Leaks, mold smell, grout dark spots | No waterproofing system, poor slope | Showers, curbless showers, benches |
| Rushed cure + poor protection | Powdery grout, tile shifting, staining | Walking too early, washing too early | Busy renos, DIY weekends |
2) Tile Installation Timeline Checklist (Fast Overview)
Use this before any install.
| Phase | Must Be True Before Moving On | Tools / Checks |
|---|---|---|
| Surface assessment | Substrate is flat, solid, clean, dry | Straightedge, level, moisture check |
| Subfloor prep | Proper underlayment + fasteners + seams | Screw pattern, seam tape, membrane plan |
| Layout | Balanced cuts, control lines, dry-lay verified | Chalk line/laser, spacers, story pole |
| Setting | Correct mortar + trowel + coverage | Trowel, mixing drill, coverage pulls |
| Grout | Joint width correct, tile cleaned, cure window met | Sponge, buckets, timer discipline |
| Movement joints | Perimeter gap and field joints planned | Backer rod/silicone, transitions |
| Protection | Traffic control + curing time | Ram board, no heavy loads too soon |
3) Phase 1 — Subfloor & Substrate Prep Mistakes (Where Most Failures Start)
Mistake #1: Tiling Over an Unstable or Flexible Subfloor
Why it fails: Tile and grout do not like bending. If the subfloor flexes, you get cracked grout, cracked tile, or loose corners.
Subfloor Risk Table (What to Watch)
| Subfloor Type | Risk Level | Common Problem | Best Practice |
|---|---|---|---|
| Old wood plank | High | Movement + unevenness | Reinforce + proper underlayment |
| Plywood (thin / unsupported) | Medium–High | Deflection causing cracks | Correct thickness + support |
| Concrete slab (new) | Medium | Moisture + shrinkage cracks | Moisture test + crack isolation |
| Concrete slab (old) | Medium | Flatness issues, old cracks | Flatten + isolation membrane |
| OSB | Medium | Swelling at seams | Proper underlayment/membrane |
“Do This / Don’t Do This” Table
| Do This | Don’t Do This |
|---|---|
| Confirm the floor feels rigid (no bounce) | Assume “it’s fine” because it doesn’t squeak |
| Reinforce before tile | Tile first and hope grout hides movement |
| Use a tile-rated underlayment system | Tile directly to plywood in risky areas |
Mistake #2: Ignoring Flatness (Especially With Large Format Tile)
Flatness is not “level.” A floor can be level and still not flat.
Flatness Requirements (Practical Rule Table)
| Tile Size | Substrate Flatness Needed | What Happens If You Ignore It |
|---|---|---|
| Small tile / mosaics | More forgiving | Still can show waves |
| 12x24 | Needs good flatness | Lippage and uneven joints |
| 24x24+ / large format | Very flat required | Lippage becomes unavoidable |
How to Check Flatness (Simple Method Table)
| Tool | What You Do | What You’re Looking For |
|---|---|---|
| 6–10 ft straightedge | Slide across floor in multiple directions | Humps/dips and gaps |
| Laser line | Shoot across surface | Waves and high points |
| Chalk line grids | Visual reference | Areas that will need filling |
Best practice: Fix flatness before opening mortar. It’s cheaper and cleaner to prep than fight tile.
Mistake #3: Tiling Over Dust, Paint, Sealer, or Construction Debris
Mortar bonds to clean, porous, stable surfaces. Dust acts like a bond breaker.
Bond Breaker Checklist
| Contaminant | Why It’s a Problem | Fix |
|---|---|---|
| Dust / drywall powder | Prevents adhesion | Vacuum + wipe + prime if needed |
| Paint overspray | Weak bond | Scrape/sand to sound surface |
| Old adhesive residue | Uneven and unstable | Mechanically remove or proper prep |
| Sealer / curing compounds | Blocks bond | Grind or use correct primer/system |
Mistake #4: Skipping Crack Isolation on Concrete
Concrete cracks. Your choice is whether those cracks telegraph into the tile.
When Crack Isolation Matters Most
| Scenario | Risk | Recommendation |
|---|---|---|
| Slab with visible cracks | High | Crack isolation membrane |
| Radiant heat slab | High | Isolation + movement joints |
| New slab | Medium–High | Moisture test + isolation plan |
| Old basement slab | Medium | Isolation if cracks exist |
4) Phase 2 — Layout & Planning Mistakes (Where “Good Installers” Separate From “Fast Installers”)
Mistake #5: Starting Without a Layout Plan (The “Sliver Cut” Problem)
Sliver cuts look cheap and create weak edges.
Cut Balance Table
| Location | Good Cut Size | Why |
|---|---|---|
| Along main visible wall | Bigger cuts | Looks intentional |
| Under vanity / behind toilet | Smaller cuts OK | Less visible |
| Doorways | Full tiles preferred | Cleaner transitions |
| Shower niche borders | Symmetry matters | High focal point |
Layout Planning Checklist
| Step | What To Do | Why It Matters |
|---|---|---|
| Find focal points | Entry view, main wall, tub line | Tile lines should “read” straight |
| Dry-lay 1–2 rows | Confirm cut sizes | Prevent slivers |
| Establish control lines | Use laser/chalk grid | Keeps tile from drifting |
| Account for grout joints | Include real joint width | Prevents layout surprises |
Mistake #6: Not Planning for Tile Variation (Shade, Pattern, Caliber)
Tile is manufactured. There can be:
-
shade variation
-
slight size differences (caliber)
-
pattern direction (especially wood-look)
Tile Variation Table (How to Avoid “Patchy Floors”)
| Issue | What It Looks Like | Prevention |
|---|---|---|
| Shade variation | Random dark/light patches | Mix from multiple boxes |
| Pattern repetition | Obvious repeated print | Shuffle tiles + rotate |
| Size variation | joints drifting | Use spacers + consistent lines |
| Warpage (some tiles) | edge lippage | Correct offset + leveling |
5) Phase 3 — Mortar, Mixing, Troweling & Coverage Mistakes
This is where many “looks okay” installs fail later.
Mistake #7: Using the Wrong Mortar for the Tile or Area
Mortar Selection Table (Practical)
| Situation | Risk | What You Need |
|---|---|---|
| Large format floor | High | Proper mortar + coverage control |
| Wet area shower | Very high | Wet-area rated system mortar |
| Tile over membrane | Medium | Compatible mortar for membrane |
| Natural stone | Medium | Mortar that supports stone stability |
| Glass tile | High | Mortar suited for glass (bond + colour) |
(Contractors usually know this, but DIY installers often grab “whatever is on sale.”)
Mistake #8: Wrong Trowel Notch (Too Little or Too Much Mortar)
Trowel Mistake Symptoms Table
| Symptom | Likely Cause | Why It Happens |
|---|---|---|
| Hollow sound | Not enough mortar / poor coverage | Wrong notch or poor collapse |
| Tile sinking / messy joints | Too much mortar | Too big notch |
| Corners loose | No back-butter | Coverage failure |
Coverage Targets (Simple Table)
| Area | Coverage Goal | Notes |
|---|---|---|
| Dry floors | High coverage | Avoid voids |
| Wet areas / showers | Very high coverage | Voids become water pathways |
Mistake #9: Letting Mortar “Skin Over” Before Setting Tile
Mortar has an open time. If it skins, it won’t bond properly.
Skinned Mortar Table
| What You See | What It Means | What To Do |
|---|---|---|
| Mortar looks dull/films over | Surface dried | Scrape and re-apply fresh |
| Tile doesn’t grab | Bond compromised | Reset with fresh mortar |
| Coverage test shows gaps | Poor transfer | Change technique + timing |
Mistake #10: Not Collapsing Ridges (Poor Bond Transfer)
You don’t want tall ridges with air gaps. You want ridges collapsed into a continuous bed.
Ridge Collapse Checklist
| Step | Best Practice |
|---|---|
| Directional troweling | Comb ridges one direction |
| Set tile with movement | Press + slide slightly |
| Pull a tile occasionally | Confirm transfer/coverage |
6) Phase 4 — Large Format Tile Mistakes (The Most Common Callback Category)
Large tiles look premium — but they are less forgiving.
Mistake #11: Using a 50% Offset on Warped Tiles
Some rectangular tiles have slight warpage. A 50% offset can magnify lippage.
Offset Guidance Table
| Tile Type | Risk | Better Offset |
|---|---|---|
| 12x24 porcelain | Medium | 1/3 offset often safer |
| Very long planks | High | Random / minimal offset |
| Perfectly flat tile | Low | More flexibility |
Mistake #12: Skipping Back-Buttering
Back-buttering helps achieve full contact, especially for large format.
| Tile Size | Back-Butter? | Why |
|---|---|---|
| Small mosaic | Not usually | Small pieces already embed well |
| 12x24 | Recommended | Improves bond and coverage |
| 24x24+ | Strongly recommended | Prevent voids and hollow spots |
Mistake #13: Not Using a Leveling System When Needed
Leveling systems don’t replace prep — but they help manage minor edge differences.
When Leveling Systems Help Most
| Situation | Benefit |
|---|---|
| Large format tile | Reduces lippage |
| Slight tile warpage | Holds edges tighter |
| Long open runs | Helps prevent “drift” |
7) Phase 5 — Wet Areas & Shower Waterproofing Mistakes (High-Stakes Zone)
A shower is not “tile + grout.” It’s a waterproofing system with correct slopes, drains, and detailing.
Mistake #14: Assuming Grout Is Waterproof
Grout is not your waterproofing. Water will move through grout lines.
Waterproofing Reality Table
| Layer | Role | Is It Waterproof? |
|---|---|---|
| Tile surface | Decorative + wear layer | Water resistant |
| Grout | Fills joints | Not waterproof |
| Waterproofing membrane | Water control layer | Yes (when installed correctly) |
| Slope/drain system | Directs water | Required |
Mistake #15: Incorrect Shower Floor Slope or Drain Planning
Slope Mistake Symptoms Table
| Symptom | Cause | Risk |
|---|---|---|
| Water pooling | Insufficient slope | Mold, staining |
| Water runs outside | Poor perimeter detail | Damage outside shower |
| Slow drain | Incorrect drain height | Constant wet surface |
Mistake #16: Not Sealing Critical Transitions (Corners, Penetrations)
Showers fail at corners, seams, benches, and pipe penetrations — not in the middle of the wall.
Shower Critical Points Checklist
| Area | Why It Fails | What Must Be Done |
|---|---|---|
| Corners | Movement + water | Proper seam treatment |
| Niches | Multiple joints | Waterproof all seams carefully |
| Benches | Flat surfaces hold water | Proper slope + waterproofing |
| Valve penetrations | Water pathway | Proper sealing detail |
| Curb top | Water sits | Slight inward slope required |
8) Phase 6 — Grout Mistakes (Colour, Cracking, Haze, and Maintenance)
Mistake #17: Choosing the Wrong Grout Colour for the Space
Grout colour affects:
-
maintenance
-
perceived cleanliness
-
how the pattern looks
Grout Colour Table
| Area | Best Grout Strategy | Why |
|---|---|---|
| Entryway | Mid-tone/darker | Hides dirt and salt |
| Shower floor | Mid-tone | Easier maintenance |
| White tile backsplash | Light or matching | Clean look, but plan sealing/maintenance |
| Patterned tile | Match dominant colour | Avoid visual chaos |
Mistake #18: Over-washing Grout (Weak, Powdery Joints)
Too much water during cleanup can weaken grout.
Over-Wash Symptoms Table
| Symptom | Likely Cause | Fix |
|---|---|---|
| Chalky grout | Too much water | Re-grout if severe |
| Crumbling joints | Weak grout mix | Remove and redo |
| Colour inconsistency | Uneven wash timing | Consistent method |
Mistake #19: Grout Haze Left Behind
Haze makes tile look dull and dirty.
Haze Prevention Table
| Step | What to Do |
|---|---|
| Work in small sections | Don’t grout the whole room at once |
| Use clean water | Change water frequently |
| Final buff | Microfiber after haze forms slightly |
9) Phase 7 — Movement Joints, Perimeter Gaps, and Transitions
This is where many “mystery cracks” come from.
Mistake #20: Grouting Tight to Walls (No Perimeter Gap)
Tile expands and contracts. If there’s no room to move, it pushes against walls and can tent.
Movement Joint Table
| Location | What You Need | Why |
|---|---|---|
| Perimeter (walls) | Expansion gap | Prevent tenting/cracking |
| Large rooms | Field movement joints | Manage expansion |
| Sunlit areas | More movement joints | Heat causes expansion |
| Heated floors | More movement planning | Heat cycling movement |
Mistake #21: Poor Transitions Between Surfaces
Bad transitions look amateur and can chip.
Transition Planning Table
| Transition Type | Best Practice |
|---|---|
| Tile to hardwood | Proper transition piece + height plan |
| Tile to carpet | Clean edge profile |
| Doorway threshold | Centered and intentional |
| Outside corners | Protect with profile |
10) Phase 8 — Curing, Protection, and First Clean
Mistake #22: Walking on Tile Too Soon
Early Traffic Risk Table
| What Happens | Why It’s Bad |
|---|---|
| Tile shifts | Breaks bond alignment |
| Grout cracks | Movement before cure |
| Corners lift | Weak bond forms |
Mistake #23: No Protection During Reno
Tile gets scratched, stained, and chipped during other trades.
| Protection Method | What It Prevents |
|---|---|
| Floor protection boards | Scratches and chips |
| No dragging tools | Edge damage |
| Controlled traffic | Early failures |
11) Troubleshooting Table: Symptoms → Causes → Fix
| Symptom | Most Likely Cause | Best Fix |
|---|---|---|
| Hollow tile sound | Poor coverage | Remove + reset affected tiles |
| Lippage | Poor flatness or layout drift | Re-set tiles; prevent with prep/leveling |
| Cracked grout lines | Movement / deflection | Add movement joints + repair grout |
| Dark grout in shower | Water trapped / slow dry | Improve ventilation; check waterproofing |
| Loose tile corners | Skinned mortar / no back-butter | Reset with correct method |
| Water pooling in shower | Slope problem | Correct slope (may require redo) |
12) Room-by-Room “Do This / Don’t Do This”
Kitchen Floor
| Do This | Don’t Do This |
|---|---|
| Matte porcelain + good prep | Polished tile where spills happen |
| Check coverage regularly | Assume coverage is fine |
| Plan transitions and door cuts | Leave thresholds as an afterthought |
Bathroom/Shower
| Do This | Don’t Do This |
|---|---|
| Use a full waterproofing system | Treat grout as waterproof |
| Mosaic floor for slope | Force large tile on shower floor |
| Seal penetrations and corners | Ignore valve/pipe details |
Entryway/Mudroom
| Do This | Don’t Do This |
|---|---|
| Mid-tone grout | Bright white grout |
| Textured/matte finish | Slick polished finish |
| Add perimeter movement gap | Grout tight to walls |
13) Contractor Handoff Checklist (Avoid Disputes & Callbacks)
| Item to Document | Why |
|---|---|
| Substrate condition + prep plan | Confirms you followed best practice |
| Layout plan + focal line | Prevents “why is it off-center?” |
| Mortar choice | Ensures compatibility |
| Coverage checks | Proof of proper bond |
| Waterproofing photos | Critical for showers |
| Movement joint placement | Prevents future cracks |
14) DIY Checklist: When to Call a Pro
DIY-Friendly Projects
| Project | Why |
|---|---|
| Simple backsplash | Low water risk, small area |
| Powder room floor | Smaller risk than shower |
| Laundry room floor | Manageable with good prep |
Call a Pro For
| Project | Why |
|---|---|
| Curbless showers | Waterproofing + slope complexity |
| Large-format open floors | Flatness tolerance is tight |
| Heated floors | Movement planning is critical |
| Complex layouts | Herringbone/diagonal with many cuts |
Final Notes (Tile Shoppe Advice That Saves Projects)
Tile installation is a system: prep + planning + bonding + movement + cure. When one part is ignored, even the best tile can underperform.